Within the framework of the project, the vendor’s hardware platform was supplied and commissioning works were performed in order to replace the existing security gate on site in Solnechnogorsk. The current software of the vendor was updated on sites in Khimki and Solnechnogorsk with the configuration migration. 12 hardware platforms of the vendor were also supplied to replace the existing equipment for remote offices of the company. Representatives of Schüco International Moscow underwent briefing and training with regard to the replacement of hardware platforms in remote offices of the company.

Modernisation of the perimeter of the distributed network was performed with minimum downtime of Schüco International Moscow services, thus ensuring the business continuity.